Google has confirmed it is the developer behind the 2.7-gigawatt Project Tembo data center in Cheyenne, Wyoming, with construction slated for completion by

Google has officially identified itself as the owner and developer of Project Tembo, a massive 2.7-gigawatt data center campus located near Cheyenne, Wyoming [1, 2]. The project, formerly known as Project Jade, represents a significant expansion of the region's data center infrastructure, which is already home to facilities from competitors including Microsoft and Meta [1, 2].

| At a glance | |
|---|---|
| Developer | Google (via Jupiter Star Holdings) |
| Capacity | 2.7 gigawatts (scalable to 10 gigawatts) |
| Location | Switchgrass Industrial Park, Wyoming |
| Completion Date | 2031 |

## Transition from Crusoe to Google
The project’s development underwent a quiet shift in recent months when Google’s subsidiary, Jupiter Star Holdings, took over construction from Crusoe [1, 2]. While Crusoe had previously paused work on the site at the customer's request, the project remained active, with the client—now revealed as Google—opting to bring development in-house [1, 2]. The 716-acre site is designed to support high-density computer workloads across four data halls, an office hub, and associated logistics and network buildings [1, 2].

Power for the campus is being managed through a combination of resources. Tallgrass Energy is developing a "bring-your-own-power" generation hub featuring natural gas turbines, while the facility will also connect to the local electrical grid managed by Black Hills Energy [1, 3]. This infrastructure strategy is part of a broader trend in the Cheyenne area, where data center growth has prompted local officials to debate whether current power and land-use planning can keep pace with the scale of incoming tech projects [1].

## Community and Regulatory Status
Google is hosting a community open house on Wednesday to provide details on the project, including its sustainability commitments and community partnerships [3]. The event follows a June 30 site-plan amendment filed with Laramie County, which publicly linked Google to the campus for the first time [1]. While the project is moving forward, it remains subject to ongoing regulatory processes, including a permit hearing scheduled for August 13 [1].

## What to watch
*   **Permit Hearing:** The Laramie County Commission is set to hold a hearing regarding the project’s permit on August 13 at 3:30 p.m. [1].
*   **Public Feedback:** The county is accepting public comments on the site-plan amendment through July 31 [1].
*   **Infrastructure Scaling:** Monitor whether the local power grid and municipal planning can support the project's potential 10-gigawatt scale, a figure significantly higher than the initial 2.7-gigawatt design [1, 3].

The emergence of Project Tembo underscores the rapid transformation of the Cheyenne region into a major hyperscale tech hub. With Google now confirmed as the primary operator, the focus shifts to how the company will integrate its massive power requirements into the existing regional energy landscape by the 2031 completion target [1, 2].

## Sources
1. Cowboystatedaily — [Say Hello To Google, The Mystery Owner Behind... | Cowboy State Daily](https://cowboystatedaily.com/2026/07/08/google-revealed-as-owner-of-wyomings-largest-data-center-now-project-tembo/)
2. Baxtel — [Google Revealed As Customer Behind 2.7GW Data Center Campus...](https://baxtel.com/news/google-revealed-as-customer-behind-2-7gw-data-center-campus-near-cheyenne-wyoming)
3. Wyoming Tribune Eagle — [Google to hold open house for Project Tembo data center](https://www.wyomingnews.com/news/local_news/google-to-hold-open-house-for-project-tembo-data-center/article_9fa73f22-94ad-4fa6-b5d1-d429985a44ed.html)
4. Tembo — [Tembo - Move coding agents to the cloud](https://www.tembo.io/)

---
Cite as: TrendWatcher, "Google Confirms Ownership of 2.7GW Wyoming Data Center", https://www.trendwatcher.in/article/d07508d0-0434-40aa-8d3b-bef8acfc1826